​New Pebble Crushing Facility

Project details The Highland Valley Copper mine is Canada’s largest open pit mine, producing both copper and molybdenum concentrates. As part of the 2011 mill optimization project, which sought to increase the mine’s average throughput by approximately ten percent, CWA designed a completely new pebble crushing circuit and crushing building including a 300-tonne surge bin,… Read More

​Primary Crusher Relocation

Project details The Highland Valley Copper mine is Canada’s largest open pit copper mine and produces both copper and molybdenum concentrates. CWA developed the project execution plan and performed the detailed civil, structural, mechanical, and electrical design for the relocation of primary crusher #4. The project included: The relocation of two 1,000-metre-long overland conveyors with… Read More